Steps to get demolition under way on schedule:
January 18th
Obtain Approvals from State and Denver agencies,
Notify Adjacent owners of demolition
February 2nd
Demolition Pre-inspection Denver Bldg. Dept.
February 5th
Obtain Demolition Permit
February 8th
Begin demolition
In order to get the demolition going, Pinkard will apply for demolition permits ahead of contract finalization.
Our Constructability Review Found
WHAT WE FOUND
Get the windows right.
123-456-7890
Find us on Facebook
Preflight Meeting

Mark Bokhoven
Mark will guide you through the estimate and work with you to make a list of add-alternates to activate if budget allows.

Joe Boeckenstedt
Joe will lead you through partnering - setting expectations for all team members to be upheld throughout the project.

Tyler Morgan
Tyler will be on hand to get the project management off to a great start and ensure that you understand the billing process.
ESTIMATE REVIEW
We are prepared to discuss any aspect of our estimate that you would find useful.
SCHEDULE DEVELOPMENT
The PLAN to get you done on time.
Schedule Shoring Permits and other early critical activities
Dial in personnel to minimize GCs.
Weekly updates, available to you in Procore.
TIME TO GO!
FINALIZE FUNDING
​
GET PRIME CONTRACT ISSUED
ISSUE KEY SUBCONTRACTS
​
​
​
​
PINKARD WILL BUY OUT DEMO AND DO PERMIT AHEAD OF TIME AT OUR OWN RISK