On the Moorhead Recreation Center project, one of our biggest quality challenges was constructing the intricate, custom foliage patterning with the exterior porcelain brick. The brick is beautiful, but it tends to be very fragile. BRS's design came with an exact template showing where every brick should go. The challenge was to get the patterning exactly correct and not damage it.

Ensuring Quality Brick Installation.


To get the brick just right, JVS Masonry created half-scale mock-ups of a brick wall section, colored and numbered each brick location, then constructed the mock-ups under the watchful eyes of Pinkard, the City, and BRS.


Once everyone agreed that the correct construction and quality approaches were understood and mastered, crews went to work on the real thing. In preparation for construction, JVS once again plotted the location and color of each brick.


During construction, five different individuals took turns inspecting the installation every two hours. This result was near perfection. Everything line-up perfectly.


Project Architect Jesse Sherr: “I think those guys did a great job with the porcelain brick. That material is probably one of the most challenging tasks and some of the best installed on that whole project.”


As construction progressed under a very tight schedule, the team continued to face one demanding quality challenge after another.


Construction Manager Blake Chambliss: “Pinkard had a tremendous number of quality/fit and finish responsibilities. We were working on a fast-paced schedule and at every turn, we encountered challenging details. The multi-purpose room ceiling clouds were a great example.”



Learn More

Recreation Construction

Recreation Construction

Moorhead Recreation Center

Moorhead Recreation Center

Share This Story

More News

Project Tour: The Spoke on Coffman

March 12, 2025

Project Tour: The Spoke on Coffman

Women in Construction Week: A Day in the Life of a Project Engineer

March 4, 2025

Women in Construction Week: A Day in the Life of a Project Engineer

Pinkard Turns Pool and Natatorium Challenges Into Opportunities

March 6, 2025

Pinkard Turns Pool and Natatorium Challenges Into Opportunities

Pinkard Construction Welcomes Mike Hager as Senior Project Manager

February 11, 2025

Pinkard Construction Welcomes Mike Hager as Senior Project Manager
3.jpg
Our Approach

Partner, Plan, BUILD.
Our approach puts YOU in control. 

Moorehead60.jpg

Services

Ground Up. Renovations. Big.
Small. We Do It all!

bottom of page