Welcome to the website for the Krisana Affordable Housing Construction project! We are pleased to provide information about the project and any associated road closures. This project is a partnership between Kentro Group and Lexton Mcdermott, making the redevelopment of this previously blighted site near Virginia Village a reality.
Contact Us
Address
4343 East Arkansas Avenue, Denver, CO, USA
Contact
303-986-4555
Working Hours
Mon - Fri
7:00 am – 9:00 pm
What is it?
151 units of housing, a vibrant retail center and ample amounts of green space
Est Completion
September 2024
Leasing Information
Check Back Soon!
Project Updates
Our goal is to keep the surrounding community informed and up-to-date on the project timeline, as well as any potential traffic impacts. We also have resources available to help anyone who has questions or concerns about the road closure or construction. Please feel free to explore the site and contact us if you have any questions. Thank you for your interest in the Krisana Affordable Housing project.
August 6, 2024
Parking Lane Closure S Birch Street & E Arkansas Avenue
Parking Lane Closure on South Birch Street & East Arkansas Avenue. Fence is approximately 4' off into the parking lane.
July 30, 2024
Parking Lane on South Birch Street & East Arkansas Avenue
Parking lane closure on South Birch Street & East Arkansas Avenue until August 30th.
July 16, 2024
Road Closure on South Birch Street & East Arkansas Avenue
South Birch Street will be closed this week, July 16th and July 17th for asphalt pour back. East Arkansas Avenue will be closed this week, July 18th and July 19th for asphalt pour back back. There are detour signs placed for navigation.
July 9, 2024
Road Closure on South Birch Street & East Arkansas Avenue
Road closure on South Birch Street on July 16th through July 17th due to asphalt pour back. Road closure on East Arkansas Avenue on July 18th through July 19th due to asphalt pour back.
June 12, 2024
Sidewalk Closure Along Birch and Arkansas
Sidewalk closure on the West side of Birch and the North side of Arkansas through end of June. This is for curb and gutter and new sidewalks being poured. Asphalt will also be patched along curb and gutter.
March 12, 2024
Krisana Project Upated 03.12.24
As one can see, the exterior finishes are progressing around the building. Over the next several weeks we will start to paint the siding and trim. It is a exciting time to see the building take shape both inside and exterior.
As of today, there are no planned shutdowns in the road or adjacent right of ways.
February 27, 2024
Arkansas Street Closure
Arkansas street is back open. Flowfill is installed temporarily until asphalt paving will occur.
February 20, 2024
Arkansas Street Shutdown
Utility subcontractor has shutdown on E. Arkansas at Birch st. Sanitary Sewer manhole is being replaced and tracking for re-opening the road early next week if there are no other unknowns found below the road.
February 13, 2024
Arkansas Closure 2.13.24 - 2.26.24
The project is currently working in the street on East Arkansas between Birch and Belair. During the dates of 2.13 - 2.26, the site contractor will be tying in to the Sanitary Sewer. Please help the crews by following the detour signs and avoiding the area.
We appreciate your assistance during this phase of work.
January 30, 2024
Krisana Project Update 24.01.30
Lots going on out here at Krisana. Interior framing has turned into drywall and all major trades are onsite! Major dust creating operations will clear up by next month as the project continues to trend towards a fall completion.
Check back in for for more break news!
December 19, 2023
Moving Forward
We are looking at getting dried in soon.
Things are moving forward...
December 5, 2023
11/28-12/5 Update
Framers are working diligently to get roof trusses set so windows can be set later this week!